Identify and document a scope, schedule, and budget (cost) risk from a past project using the risk meta language:
“Because of <cause>, <risk> might occur, which would lead to <effect>. The impact on the project would be <consequences>. We will respond if <trigger>.”
Please note that there is no rubric for this assignment; it is evaluated based on the structure above, and the example below provides additional guidance of what is expected.
Example: A Construction Project
Because of sudden storm, a flood might occur, which would lead to damaged construction equipment and materials and delays in deliveries. We will respond to the potential impacts of storm flood waters.
(I will upload a sample assignment under here hope will be helpful)