QUESTION 1 25 points Save Answer Based on information below and knowing that the project planned…
QUESTION 1 25 points Save Answer Based on information below and knowing that the project planned completion duration is 20 days determine: 1. Use MS project to estimate project duration and critical path assuming there are no constraints on resources. (10 points) 2. Determine the project duration if only two programmers are available? Provide the early starting week for each task (10 points) 3. Determine the average resource utilization of programmers (5 points) Activity Duration (weeks) Predecessor Programmers 3 A 2 B 6 A 2 C 10 A 1 D 11 A 1 E 8 B 1 F 5 C D il E, F 2 G 6 For the toolbar, press ALT+F10 (PO or ALTHEN+F10 (Mac).