You want to calculate the SPI for your publishing project at the current date. If the current…
- You want to calculate the SPI for your publishing project at the current date.
If the current earned value is $50,000 and the planned value is $65,000, what is the SPI, rounded to two decimal points?
Select one:
a. 0.77
b. 1.30
c. 0.76
d. 0.769
- 2. What items are required to control the project schedule?
Select one or more:
a. The project management plan
b. Project documents such as the project schedule and project calendars
c. Work performance data
d. Organizational process assets such as monitoring and reporting methods
e. Activity lists
f. Project budget
- 3. You want to use three-point estimating based on the beta distribution to determine accurate duration estimates for project activities.
Which formula do you use to determine a three-point estimate based on the beta distribution?
Select one:
a. Duration equals pessimistic plus optimistic plus 4 times the most likely divided by 6
b. Duration equals the sum of the durations multiplied by the weights of the durations, which is then divided by 6
c. Duration equals the product of the weighted durations divided by 6
d. Duration equals the sum of the estimates multiplied by 4 and then divided by 6